Email Us

TITAN Formwork

  • TITAN Formwork

    Used TITAN Formwork HV Shoring System in Excellent condition. NOW AVAILABLE 11/6/2023 This is a large quantity of Titan formwork materials available at a great price.

    Reach National Forming to discuss Titan formwork further.

    National Forming, Co.
    Phone: (888) 367-7553
    We specialize in TITAN Formwork Shoring

  • TITAN Formwork Slab forming system The aluminum slab formwork system can be adapted to fit any plan layout with just four main components. On taller buildings erecting the formwork for cantilevering slabs, perimeter down stand beams, spandrel panels, etc. is more time consuming than standard floor bays. Furthermore, such work is very dangerous. In such cases TITAN Formwork is TITAN Formwork with the TITAN Formwork RT edge table. The complete edge table is repositioned in where formwork has to be erected for down stand beams, TITAN Formwork U- represents the ideal solution. The TITAN Formwork U- beam clamps can be reused at the same rate as the TITAN Formwork system. TITAN Formwork U- supported on trimmer beams the next storey by crane prior to beginning formwork erection so that the formwork for the critical perimeter zones is positioned first and the TITAN Formwork slab forming system can then be set up against this. TITAN Formwork is the tried-and-tested aluminum slab forming system that allows every formwork task to be carried out quickly and economically – and without time consuming and costly adaptation or make-up panels. TITAN Formwork is a modular system that is not dependent on crane handling. The concept In contrast to conventional flexible formwork systems, in the TITAN Formwork system the main beams and secondary beams are fixed in the same plane. This is possible thanks to the support ledges on the main beams and drop-heads, onto which the incoming beams are hooked. The uneconomical overlapping of beams – the situation with conventional formwork – is absent from the TITAN Formwork system. The beams form an interlocking grid that is stable in itself – even without any plywood sheeting. Nevertheless, TITAN Formwork is still fully flexible: by changing the direction of the span (simply fit main beams together at 90°), the grid can be adapted as required to fit any plan layout. Interruptions such as columns, wall corners, make-up panels, curved walls, etc. are therefore no longer a problem. The main and secondary beams can be arranged to suit. The system is complemented by the panel. This consists of an aluminum frame with an integral 10 mm GFRP sheet. These panels are fitted between the main beams instead of using secondary beams plus separate 0.5 x 2.0 m plywood sheets. Make-up areas are systematically closed off with main and secondary beams plus 21 mm plywood sheeting. The drop-head system enables the formwork to be struck just two days after concreting without having to remove the props (post shores). All the main and secondary beams (or formwork panels) are then available for the next concreting operations. Practical experience has shown that the TITAN Formwork system reduces the time needed for erecting and striking formwork considerably when compared to conventional slab formwork. This means that just two uses per month are enough to recoup the cost of hiring the components. The erection of TITAN Formwork is very easy and quick to learn. Countless uses on building sites all over the world have proved this. A two-person formwork crew can work independently. The erection of the formwork can begin at several places simultaneously using several formwork crews. For transport on site without the need for cranes, the components should be stored in wheeled storage racks “Barelle”. Setting up the formwork is carried out: without having to set out the prop spacing beforehand because the props are automatically positioned by the lengths of the beams with just 0.4 props/m² on average without unnecessary extra props “just to make sure” because the system does not permit any additional props safely because the erection work is carried out from below ergonomically and with minimal fatigue The plywood sheeting is selected according to the desired soffit finish, the number of reuses and the availability – irrespective of the system. So in contrast to panel systems, you only pay for the plywood face quality you really need. The standardized, easy-to-use three-ply 0.5 x 2.0 m sheets with edge protection have proved worthwhile for standard solutions. The plywood sheeting is laid in the same direction as the main beams. In order to release as many sheets as possible when striking early, they should not be butt-jointed over the main beams. We will be happy to send you a handy slide rule for determining the suitable beam TITAN Formwork and choice of prop for the desired slab depth. The gap above a main beam between adjacent panels is closed off with a special filler strip. The drip profiles on the underside of the filler strip ensure that any cement slurry seeping through drips off directly without leaving any unsightly stains on the main beam below. The two integral expansion joints compensate for expansion movements on hot days. Junction with perimeter wall The gap between an panel and a wall is closed off with a special filler strip. The wall spacer ensures that the perimeter main beam is positioned at the correct distance from the wall. This means that the erection of the slab formwork can begin in a corner. The swivel connection, on one side allows the erection and stripping from the bottom.

    National Forming, Co.
    Phone: (888) 367-7553
    We specialize In TITAN Formwork

Interested in a similar system? Reach us at 888-367-7553